Construction and commissioning of repowering project
2023 Phase 1: New construction of 2 GE/3.8 MW, 2 GE/5.5 MW
2025 Phase 2: New construction of 1 Nordex N133/4.8 MW
Phase 1: New construction of 2 GE wind turbines with 3.8 MW, hub height 85 m
2 GE wind turbines with 5.5 MW each, hub height 120.9 m
total 18.6 MW
- Cooperation with Danish operators of the old plants
- Compensation measure: dismantling of old livestock facility at Schrepkow
- Schrepkow substation with conversion to VDE-AR_N 4120 and TAB 3030
- Power supply of approx. 38,000,000 kWh/a
Special:
Surrounding communities receive an annual payment of €10,000 per newly constructed turbine in accordance with Brandenburg’s Windenergieanlagen-Abgabengesetz (Wind Energy Turbine Levy Act).
Commissioning of phase 1: 2023
2nd construction phase: Expansion of the 1st construction phase by 1 Nordex N133/4.8 MW, hub height 82.5 m
- Construction of access roads and crane site (length of access road 450 m)
- Foundation construction including civil engineering
- Cable engineering including communication technology (length of cable route 470 m)
- Implementation of ecological construction supervision
- Expansion of delivery route from transfer point
- Link to grid connection point with overload of existing substation
- Ensuring all tests and approvals
Commissioning of 2nd construction phase 6/2025