24 MW Awarded and Approved




With the greenwind repowering project in Ohlenbüttel, which has now received the award from the Federal Network Agency, greenwind is developing its second project in Lower Saxony. More projects will follow.

A Nordex 163.6MW turbine will be installed here, replacing an NM 100/60. As part of the municipal participation scheme, 0.3 ct/kWh will go to the municipalities within a 2.5-kilometre radius. In addition, the substation will be built on a plot of land owned by the municipality. Together with the municipality, we are developing an attractive design for this area.

Construction of the wind turbine is scheduled to begin in the middle of next year, with commissioning planned for the end of 2027.

Furthermore, the Pritzwalk-Giesensdorf wind energy project in Brandenburg, consisting of three N149-5.70 MW wind turbines, has now received approval after several delays. Legislative changes and the discovery of a red kite nest nearby contributed to these delays. However, uncertainties are part of the approval process, and greenwind navigates them with patience and perseverance!

Construction of the Pritzwalk-Giesensdorf project is scheduled to begin in early 2027, with commissioning planned for early 2028.

The development of both projects is being led by Pascal Peters, Head of greenwind’s Northern Germany regional office, based in Lübeck. Construction management will be handled by Green Wind Construction GmbH.